
OWNER:
Acheson Colloids
Contact:
Mike Card
ENGINEER:
Mc Clurg & Associates
Contact:
Robert Cooper
GENERAL CONTRACTOR:
R A Card
Construction
PILING CONTRACTOR:
Faust
Corporation
Contact:
Marc Faust
(586) 445-2030
CONTRACT DETAILS
Project Duration:
1 Month
SCOPE
OF WORK:
Supply Sheet Pile
Install Sheet Piles
PROJECT OVERVIEW:
To facilitate construction of a new building sheet piling was installed
along both side of the building site to help shore the soils and help
support the foundations of adjacent buildings during sub level excavation.
Due to the tight work spaces the sheeting had to be installed in
stages along both sides of the excavation area because there was not enough
room to operate the crane.
UNIQUE SOLUTIONS:
Initially the sheet was to be installed using a vibratory hammer. Due to the
outside wall condition of an adjacent building there was a concern that the
constant vibration could cause a collapse of the wall. To lessen the amount
of vibration an Hydraulic Impact Hammer was used to install the piles.
The use of the impact hammer lowered both the intensity and duration
of potentially damaging vibrations.
With the impact hammer the job was completed without incident.