
OWNER: Reynolds Aluminum

Contact:
ENGINEER: Metcalf & Eddy
Contact:
DREDGING CONTRACTOR:
Faust Corporation
Contact: Marc Faust
CONTRACT DETAILS
Contract Duration:
8 Months
SCOPE of WORK: Install Sheet Pile to Enclose Dredge Area
Install Silt Curtains to segregate “Hot” Areas
Install Air Curtain Gates
Construct Offloading Dock
Dredge Contaminated Sedime
PROJECT
OVERVIEW:
A portion of the shoreline and river adjacent to Reynolds Aluminum (now
Alcoa) was contaminated with high levels of PCBs and PAHs. Faust Corporation
was contracted as the Prime Dredging Contractor as part of the sediment
remediation project. To prevent possible downstream transportation of
re-suspended sediment the entire dredge area was enclosed within a steel
sheet pile wall. The dredge area was
divided into areas of high and low PCB concentrations. The high
concentration areas were enclosed with silt curtains and air curtain gates
were installed to allow for the movement of marine equipment.
Sediments were removed from the river using an environmental level
cut clamshell bucket, placed into sediment scows and transported to the
unloading dock. At this point the material was loaded into trucks and hauled
to the dewatering/stabilization area before transport to the disposal
facility
UNIQUE
SOLUTIONS: